Hungerford 2010+ Planning Project: Programme as at 15 /05/05
Date Activity
  Phase 1: Start Up (to end June)
13/05/2004 Launch event: (Town Hall)
14/06/2004 Steering group meets
29/06/2004 All Work Group: Establish Work Group members (Town Hall 7.30pm)
  Define study area beyond Hungerford
  Work groups meet to clarify members & chairmen
   
  Phase 2: Community Audit / Snapshot (July to end Sept)
  Action groups meet and progress snapshot
  Start to input Snapshot to Steering Group
   
19/07/2004 Steering Group meeting (7.30pm)
   
  Progress Snapshots in groups and input to Steering Group
16/08/2004 Steering Group meeting (7.30pm)
14/09/2004 Steering Group meeting (7.30pm)
  Phase 3: Emerging Vision (by end Nov)
  Work Groups complete Snapshot & input to vision
12/10/2004 Steering Group meeting (7.30pm)
02/11/2004 Steering Group meeting (7.30pm)
08/11/2004 Public Forum (British Legion 7.30pm)
11/11/2004 Hungerford Forum
   
  Phase 4: Detailed Analysis by Study Groups & Survey (Oct - end Feb 05)
  Work Group progress Healthcheck Worksheets
  Produce Statement of Community Involvement (SCI)
  Carry out consultation / engagement with community
  Analysis & presentation of consultations
  Progress and complete Healthcheck Worksheets
  add more here
   
  Steering / All Work Groups meetings during Phase 4
16/11/2004 Steering Group meeting (7.30pm)
30/11/2004 Steering Group meeting (7.30pm)
14/12/2004 Steering Group meeting (7.30pm)
11/01/2005 Steering Group meeting (7.30pm)
25/01/2005 Steering Group meeting (7.30pm)
08/02/2005 Steering Group meeting (7.30pm)
10/02/2005 Public Forum (Football Club 7.30pm)
22/02/2005 Steering Group meeting (7.30pm)
   
  Phase 5: Produce Vision Statement (by end March 05)
  Work Groups to progress vision statement by topic
  Steering group to coordinate
08/03/2005 Steering Group meeting at John O Gaunt (7.30pm)
13/03/2005 Steering Group Vision Brain Storming
22/03/2005 Steering Group meeting(7.30pm)
30/03/2005 Send out surveys to each household
12/03/2005 Steering Group meeting(7.30pm)
   
   
  Phase 6: Proposals, Solutions & Partnerships (by end June 05)
  Survey analysis input to draft plan
  Produce survey questionnaire & analyse
  Work Groups to progress proposals statement by topic
  Steering group to coordinate
12/04/2005 Steering Group meeting (7.30pm)
17/05/2005 Steering Group meeting (7.30pm)
  Survey printed and handed out by May 25th
07/06/2005 Steering Group meeting (7.30pm)
  All questionnaire returns by June 10th & analysis completed by June 17th
  Draft Plan completed June 24th
28/06/2005 Steering Group meeting (7.30pm)
  Phase 7: Promote & Publish Plan (by end July 05)
  Work Groups to finalise plan sections
  Steering group to coordinate & complete
  Final consultation with West Berks, Town & Manor and HTC
  Plan finalised, art work etc…
12/07/2005 Steering Group meeting (7.30pm)
  Printing of Plan
26/07/2005 All Work Group members: Launch of Town Plan (British Legion / Town Hall 7.30pm)
  Distribution of Plan
   
  Phase 8: Implementation of Proposals & Partnerships
  By Work Group identify projects to implement
  Short term: to end 2005
  Medium term: 2006 - 2008
  Longer term: 2009 - 2011
  Long term: beyond 2011
20/09/2005 Steering Group meeting (7.30pm)
   
  Phase 9: Review & Monitoring of Proposals & Partnerships
  Steering Group meetings, say every 3 months to 2008
  Steering Group meetings, say every 6 months 2009 - 2011
   

 